Mittal's City Mall
Saturday, December 25, 2010
Friday, December 3, 2010
Monday, November 22, 2010
Tuesday, September 22, 2009
Mittals City Mall-Bathinda
( Status as on 22/09/2009)
1. Ready for fit outs in all respects.
2. External and internal Façade Completed.
3. Flooring, POP, Internal & External Paint, Fall ceiling, Railing in stairs and Atrium & Roof on Atrium completed.
4. Shops fronts has been fixed with clear toughened glass with one openable door.
5. Signage’s, internal & External Lighting has been completed.
6. Landscaping (Including hard & soft) completed.
7. Access Roads from Main Road (G.T.Road) and Amrik Singh Road has been Completed
Services Completed as below
1. Lifts
2. Escalators
3. Fire fighting systems
4. Fire alarm system
5. Electrical (HT,LT,DG.)
6. Air conditioning systems.
Hotel at City Mall (Bathinda)
1. Hotel interior and Services work are in progress on war scale.
2. Swimming Pool CompletedHotel Entrance Lobby, Banquet Hall, Restaurant, Coffee, & Bar Shops, Gym etc. interior works and services work are in Progress
( Status as on 22/09/2009)
1. Ready for fit outs in all respects.
2. External and internal Façade Completed.
3. Flooring, POP, Internal & External Paint, Fall ceiling, Railing in stairs and Atrium & Roof on Atrium completed.
4. Shops fronts has been fixed with clear toughened glass with one openable door.
5. Signage’s, internal & External Lighting has been completed.
6. Landscaping (Including hard & soft) completed.
7. Access Roads from Main Road (G.T.Road) and Amrik Singh Road has been Completed
Services Completed as below
1. Lifts
2. Escalators
3. Fire fighting systems
4. Fire alarm system
5. Electrical (HT,LT,DG.)
6. Air conditioning systems.
Hotel at City Mall (Bathinda)
1. Hotel interior and Services work are in progress on war scale.
2. Swimming Pool CompletedHotel Entrance Lobby, Banquet Hall, Restaurant, Coffee, & Bar Shops, Gym etc. interior works and services work are in Progress
Thursday, March 12, 2009
Mittal's City Mall-Bathinda
As on date Mittals Citi Mall-Bathinda is ready for fit outs, as you have seen the pictures attached with this blog. External work has been completed with all respect such as Facade, Signages, Landscaping, Lighting. Flooring, POP, fall ceiling, Railing, has been done in atrium and in all passages.
Services
Lifts, escalators, fire fighting systems, Fire alarm system , electrical (HT,LT,DG.) and air conditioning systems has been installed.
Shops & Showrooms
Shops & Showrooms fronts are completed with the toughened glass. Hotel work is also in progress on war scale.